Capacity Planning and Calculation play a very important role in whole MRP-II cycle. Here is the example to calculate capacity as per available machines, labors and hours.
An Example
•Simple, near perfect world
1 machine, no labor or material constraints
•Annual demand 1.2 million units
•Rated equipment capacity :
300 units per hour
1 machine, no labor or material constraints
•Annual demand 1.2 million units
•Rated equipment capacity :
300 units per hour
Assumptions
Enough capacity?
How much annual capacity ?
DAYS
365
-100 weekends
265
-15 holidays
250 “regular” days
HOURS
8 gross time / shift
-1 breaks
7 productive time
x3 # shifts
21 net hours / day
250 days/year x 21 hours/day = 5250 hours/year
5250 hours/year X 300 units per hour = 1.575 mm
Capacity utilization = 1.2 / 1.575 mm = 76%